October Clubhouse Update

We’re making good progress on the Clubhouse and Athletic Center, and it’s great to see more of the finishing touches starting to come together.

Inside, all the windows are now installed in the Clubhouse, Fitness Center, and Function Hall. Drywall is about 85% complete, painting has started, and floor tile installation gets underway this week. The spaces are really starting to look like the finished product.

Outside, work continues on the service drives, sidewalks, cart paths, and patios. The patio behind the Clubhouse is beginning to take shape, and landscaping and privacy screening around the pool are now complete.

There’s still plenty of work ahead, but we’re seeing real progress every week, and we remain on track to have a functioning Clubhouse in the first quarter of next year!